Stoughton flag  
2017 Street Reconstruction Project

This year's street reconstruction project  includes total reconstruction of Harrison Street from Hamilton Street to Main Street, Division Street from Washington Street to 233 N. Division Street, Brickson Street from Page Street to the River, Manilla Street from Brickson Street to Forton Street, Park Street from Lynn Street to Academy Street, and Henry Street from Main Street to Ridge Street.  The reconstruction project will include total street removal and reconstruction, spot sidewalk replacement and infill, driveway apron replacement and underground utility work.  In addition, the project includes some underground utility work in Milwaukee Street between Monroe Street and Page Street.

If you have questions about this project please contact Director of Planning & Development Rodney Scheel at 608-873-6619 or rjscheel@ci.stoughton.wi.us

A project Open House was held on February 1, 2017 where all adjacent property owners were invited.  It was attended by about 30 people.

Special assessment materials are being prepared and will be distributed to affected property owners the week of March 13, 2017.  A public hearing related to the special assessments will be held on April 25, 2017 at 7:00 pm in the Council Chambers.

Contractor provided schedules can be seen at the bottom of this page.  Schedules will changes, but this is the information provided by the contractor on how they plan to manage this project.

 

Work Anticipated for the week of: 8/21/17-8/25/17

 

  • Harrison, Park/Lynn, and Henry/Giles

    • Surface paving is schedule to start on August 30th and 31st

  • Division Street

    • Sidewalk and apron pours will be completed by Tuesday.

    • Terrace grading and restoration crews will be present later starting on Thursday the 24th and will likely run through the Monday 28th.

    • Road grading on Division Street will start on August 29th.

    • Binder paving is scheduled to occur on August 30th. Surface paving will occur the following day on the 31st.

    • Street work and restoration to be completed and open on September 1st

  • Brickson/Manilla Street

    • Utility crews will finish the remaining storm sewer by Tuesday.

    • Road grading crews will begin subgrade work by Wednesday.

    • Curb and gutter pours is expected during the week of the 28th

  • Milwaukee Street

    • Utility crews may mobilize to project area later in the week to start with water main installation.

 

Work Anticipated for the week of: 8/14/17-8/18/17

 

  • Harrison, Park/Lynn, and Henry/Giles

    • Paving is not intended to occur until later this August. 

  • Division Street

    • Curb and gutter will be poured on Monday. Sidewalk and driveway apron pours will occur throughout the remainder of the week. 

  • Brickson/Manilla Street

    • Utility crews will continue with water service and sewer lateral replacements early in the week.

    • Utility crews will start installation of storm sewer on Brickson Street. 

  • Milwaukee Street

    • Utility crews may mobilize to project area later in the week to start with water main installation.

 

Work Anticipated for the week of: 8/7/17 – 8/11/17

 

  • Harrison, Park/Lynn, and Henry/Giles

    • Paving is not intended to occur until later this August.

  • Division Street

    • Subgrade crews will continue with road building efforts. Work is expected to occur from the North Street intersection to the Washington Street intersection. Crews will be excavating roadway and placing gravel. Access to driveways will be difficult during daytime activities. Alternative off project parking should be anticipated. Access to driveways will be restored at each days end.

    • Curb and gutter is tentatively in the schedule for the later part of the week. Notification will be provided to residents ahead of this effort. 

  • Brickson/Manilla Street

    • Utility crews will continue with water main work followed by sanitary sewer replacement on Brickson Street throughout the early part of next week. After sampling and testing it is anticipated that water service and sewer lateral work will occur during the later part of the week.

 

Work Anticipated for the week of: 7/31/17 – 8/4/17

 

  • Harrison, Park/Lynn, and Henry/Giles

    • Paving crews have expressed interest in completing the final surface work this week. An effort will be made to review this intention early next week and notification to residents prior to paving will be provided.

  • Division Street

    • Complete water main connection at the Division and North Street intersection after a safe water sample has been obtained and pressure testing has been successful.

    • Complete installation of Inlets 7.2, 7.3, 7.4, and their associated pipe runs after completion of water main connection.

    • Subgrade crews will begin on Tuesday working from the North end of Division Street. Crews will be excavating roadway and placing gravel. Access to driveways will be difficult during daytime activities. Alternative off project parking should be anticipated. Access to driveways will be restored at each days end.  

  • Brickson/Manilla Street

    • Utility crews will begin with water main work starting near the Manilla and Forton Street intersection. Water main outage associated with the connection is planned for Monday morning and the affected properties have been notified by the contractor.

 

 Work Anticipated for the week of: 7/24/17 – 7/28/17 

  • Park, Henry, and Giles Street

    • Landscaping crews will continue with terrace restoration (weather permitting).

  • Division Street

    • Storm sewer installation along Division Street will continue early in the week.

    • Water main installation at the Division and North Street intersection will occur during the middle part of the week.

    • Subgrade work on the Northern portion of Division Street between the boathouse and the North Street intersection may occur later in the week.

 

Work Anticipated for the week of: 6/19/17 – 6/23/17 

  • Park, Henry, and Giles Street

    • The general contractor will continue with terrace grading early in the week.

    • Asphalt saw cutting of roadway pavement at the project limits is scheduled to occur Monday afternoon.

    • Asphalt subcontractor will begin road grading later in the week.  Binder paving is anticipated to occur early the week of the 26th.

  • Harrison Street

    • The general contractor will continue with terrace grading early in the week.

    • Asphalt saw cutting of roadway pavement at the project limits is scheduled to occur Monday afternoon.

    • Asphalt subcontractor will begin road grading later in the week. Binder paving is anticipated to occur early the week of the 26th.

 

Work completed for the week of: 6/12/17 – 6/16/17 

  • Monday – Concrete work on Harrison Street started with placement of string line and gravel grade preparation between the Main and Hamilton Street intersection. No work occurred on the Park, Henry, or Giles Street project areas.

  • Tuesday – Concrete work on Harrison Street resumed with installation of the curb and gutter between the Main and Hamilton Street. The general contractor started with terrace grading site cleanup at the Park, Henry, and Giles Street project areas.

  • Wednesday – Concrete work on Harrison Street resumed with sidewalk form placement and grading. The general contractor completed manhole and water valve casting adjustments at the Park, Henry, and Giles Street project areas. They also adjusted water service curb stop boxes and continued with terrace grading and site cleanup. Storms brought heavy rains and stopped work early in the afternoon.

  • Thursday – Concrete work on Harrison Street resumed with installation of sidewalk between the Main and Hamilton Street Intersection. The general contractor continued terrace grading and site cleanup at the Park, Henry, and Giles Street project areas.

  • Friday – Concrete work on Harrison Street resumed with sidewalk form placement and grading. Crews resumed with sidewalk, ramp, and apron installation between the Main and Hamilton Street Intersection. The general contractor continued terrace grading and site cleanup at the Park, Henry, and Giles Street project areas. 

Work completed for the week of: 6/5/17 – 6/9/17 

  • Monday – The concrete subcontractor setup forms in preparation of the valley gutter work on Henry Street. Crews also started with placement of forms for sidewalk on Park, Henry, and Giles Street. The general contractor started terrace and sidewalk grading on Harrison Street.

  • Tuesday – The concrete subcontractor poured the valley gutters on Henry Street. Crews started with sidewalk, ramp, and apron pour on Henry Park, Henry, and Giles Street. The general contractor continued with terrace and sidewalk grading on Harrison Street.

  • Wednesday – The concrete subcontractor continued to setup forms for sidewalk, ramps, and aprons at the Park, Henry, and Giles Street project areas.

  • Thursday – The concrete subcontractor continued with sidewalk, ramp, and apron pours on Park, Henry, and Giles Street. Crews setup sidewalk forms for the sidewalk meandering through the City park along the South side of Park Street

  • Friday – The concrete subcontractor continued with sidewalk, ramp, and apron pours on Park, Henry, and Giles Street. Crews poured the sidewalk meandering through the City park along the South side of Park Street.

Work completed for the week of: 5/29/17 – 6/2/17 

  • Monday – No work occurred, Memorial day.

  • Tuesday – The general contractor continued with road building on Harrison Street working North towards the Hamilton Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.  Utility crews excavated to remove the repair sleeve and conduct a more appropriate repair in conjunction with the adjacent hydrant abandonment near the Harrison and Hamilton Street intersection.

  • Wednesday – The concrete subcontractor started with placement of string line for curb and gutter and gravel preparation at the Park, Henry, and Giles Street project areas. The general contractor completed the remaining road building work on Harrison Street.

  • Thursday – The concrete subcontractor continued with placement of string line for curb and gutter and gravel preparation at the Park, Henry, and Giles Street project areas.

  • Friday – The concrete subcontractor started with installation of curb and gutter on the Park, Henry, and Giles Street project areas. Curb work on Park Street was nearly completed with the exception of a few small curb patch section at the Academy intersection. Curb work on Henry and Giles was nearly completed with the exception of the valley gutter work at the two intersections. 

Work completed for the week of: 5/22/17 – 5/26/17 

  • Monday – The general contractor continued with road building on Henry Street working North towards the Ridge Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed. Utility crews on Harrison Street continued with water service and sanitary sewer lateral replacements.

  • Tuesday – The general contractor completed the remaining road building on Henry Street. Approval to continue with full street replacement on Giles Street was approved and they started with road building on Giles Street. Utility crews on Harrison Street continued with water service and sanitary sewer lateral replacements.

  • Wednesday – The general contractor continued with road building on Giles Street working West towards the Morris Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed. Utility crews on Harrison Street continued with water service and sanitary sewer lateral replacements.

  • Thursday – The general contractor completed the remaining road building work on Giles Street. They also started with road building on Harrison Street. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.

  • Friday – The general contractor continued with road building on Harrison Street working North towards the Patterson Street intersection. Unsuitable subgrade material was encountered and subgrade stabilization methods were employed.

 Work completed for the week of: 5/15/17 – 5/19/17 

  • Monday – Utility crews on Harrison Street continued with sanitary sewer installation. Utility crews on Giles Street started with water service replacements.

  • Tuesday – Utility crews on Harrison Street continued with sanitary sewer installation. Crews completed the mainline work after connecting to the existing manhole at the Hamilton Street intersection. Utility crews on Giles Street continued with water service replacements.

  • Wednesday – Utility crews on Harrison Street started with sanitary lateral replacements in the morning. Utility crews on Henry and Giles Street completed the final water main connection at the Giles and Morrison intersection as well as abandoned the last remaining portion of existing water main. All work was halted promptly before noon after wet weather dominated the remainder of the workday.

  • Thursday – Utility crews on Harrison Street installed the new fire hydrant near the Hamilton Street intersection as well as the new main and fire hydrant at the Patterson Street intersection. Road crews began subgrade work on Park Street near the Main Street intersection. Unsuitable subgrade materials were encountered and subgrade stabilization methods were employed.

  • Friday – Utility crews on Harrison continued with began water service and continued sanitary lateral replacements. Road crews on Park Street continued with subgrade work near the Giles Street intersection.  

Work completed for the week of: 5/8/17 – 5/12/17

  •  Monday – Utility crews on Park Street abandoned the existing water main along Park Street and installed San MH-8 at the Academy Street intersection. Utility crews on Giles Street began water main installation starting at the Morris Street intersection. They installed the new fire hydrant at the Southeast corner of the intersection.
  • Tuesday – Road crews continued with road building on Park Street. Unsuitable subgrade material was encountered and road stabilization methods were employed. Utility crews continued with water main installation working East along Giles Street.

  • Wednesday – Road crews continued with road building on Park Street. Unsuitable subgrade material was encountered and road stabilization methods were employed. Utility crews began water service and sanitary lateral replacements on Henry Street. Utility crews began sanitary sewer replacement on Harrison Street and installed San MH 0 and 1.

  • Thursday – Road crews continued with road building on Park Street. Crews continued placement of road base in preparation of curb and gutter installation. Utility crews on Giles Street made the water main connection to the existing main on the East side of the Henry Street intersection. Utility crews began water service and sanitary lateral replacements on Henry Street. Utility crews continued with sanitary sewer replacement working North along Harrison Street.

  • Friday – Utility crews on Henry Street continued with sanitary sewer lateral replacements. Utility crews continued with sanitary sewer replacement working North along Harrison Street.

Work completed for the week of: 5/1/17 – 5/5/17

  •  Monday – Water main replacement resumed on Henry Street and the utility crews were able to complete the water main connection at the Henry and Main Street intersection. Utility crews on Lynn Street completed the remaining sanitary sewer replacement after connecting the existing manhole South of the Park Street intersection.
  • Tuesday – Utility crews on Park Street made the water main connection at the Park and Lynn Street intersection. The crews also started with sanitary sewer lateral and water service replacements. Utility crews on Henry Street started with sanitary sewer replacement working West along Giles Street.

  • Wednesday – Utility crews on Park Street continued with sanitary sewer and water service replacement. Utility crews on Giles Street continued with sanitary sewer replacement.

  • Thursday – Utility crews on Park Street continued with sanitary sewer and water service replacement. Utility crews on Giles Street continued with sanitary sewer replacement. Crews completed sanitary sewer replacement after installing San MH-11.

  • Friday – Utility crews on Park Street completed the abandonment of the existing water main along Park Street by capping the existing main at the Academy Street intersection. Crews also installed San MH-8 and abandoned the existing sanitary sewer along Park Street. Utility crews started with water main replacement on Giles Street working East from the Morris Street intersection. Crews installed the new fire hydrant at the Southeast corner of the intersection. 

Work completed for the week of: 4/24/17 – 4/28/17

  •  Monday – Sanitary sewer replacement resumed on Henry Street. Utility crews on Henry Street installed MH San-10. Once finished with the manhole installation, utility crews made a connection to the existing water main in the Henry and Ridge Street intersection. Water main replacement resumed on Park Street. Utility crews installed the new fire hydrant mid-block along the South side of Park Street.
  • Tuesday – Water main replacement resumed on both Henry Street and Park Street. Utility crews on Henry Street completed water main installation to the Giles Street intersection. Utility crews on Park Street completed water main installation to the Lynn Street intersection. Once finished with water main installation, utility crews began installation of sanitary sewer South along Lynn Street.

  • Wednesday – Utility crews for both Park and Henry Street were able to work for a couple hours early in the day before being rained out the remainder of the workday.

  • Thursday – No work occurred due to wet weather. Water main connection at the Main and Henry Street intersections has been rescheduled to Monday morning.

  • Friday – Water main replacement resumed on Henry Street and sanitary sewer replacement resumed on Lynn Street.

Work completed for the week of: 4/17/17 – 4/21/17

  • Monday – Sanitary sewer replacement began on both Park Street and Henry Street. Utility crews on Park Street installed MH San-7 at the Academy Street Intersection and proceeded with installation of new sanitary sewer working West along Park Street. Utility crews on Henry Street connected to the existing sanitary manhole at the North side of the Main Street Intersection and proceeded with installation of new sanitary sewer working North along Henry Street.

  • Tuesday – Sanitary sewer replacement resumed on both Park Street and Henry Street. Utility crews on Park Street installed MH San-6.

  • Wednesday – Sanitary sewer replacement resumed on both Park Street and Henry Street. Utility crews on Henry Street installed MH San-9.

  • Thursday – Sanitary sewer replacement resumed on both Park Street and Henry Street. The utility crews on Park Street reached the Lynn Street intersection and completed sanitary sewer installation after installing MH San-4 and 5. The utility crews finished the day short of MH San-10.

  • Friday – Water main replacement began on Park Street. Utility crews made connection to the existing water main in the Academy Street Intersection and proceeded with new water main installation working West along Park Street. Crews installed the new fire hydrant at the Southwest corner of the intersection.